PLACEMENT
AND PIPEJACKING PROCESS FOR METAL JOINTS |
1.-GENERALITIES
As part of the construction and pipe-jacking of the 2.44, 2.13 and 1.83
m diameter collector piping, it will be necessary to place a temporary
cofferdam and scaffolding system to allow the excavation to be done while
preventing any water filtration into the ditch during the construction
process.
To that end, the use of a scaffolding system has been proposed, that consists
of a metal cofferdam supported by a group of joists located placed throughout
the rest of the lateral excavation walls.
This specification provides the general guidelines and necessary recommendations
that should be followed exclusively for the driving and placement of the
metal cofferdam.
The driving of cofferdam metal plates will be carried out with mechanical
equipment powerful enough to drive plate’s outer wall into the pipe.
The following steps are the stages into which the construction process
has been subdivided, and it is also applicable to the construction of
the access port, making note of some restrictions which will be outlined
later.
PERIOD I.-REMOVAL OF EXCISTING
INSTALLATIONS AND STRUCTURES
PERIOD II.- GUIDE INSTALLATION
PERIOD III- COFFERDAM PLATE DRIVING
PERIOD IV.- COFFERDAM PLATE REMOVAL
2.-CONSTRUCTION PROCEDURE
The following is a detailed procedure to be followed during cofferdam
plate driving, plate placement, and plate removal activities.s.
STAGE 1. - REMOVAL OF EXCISTING
INSTALLATIONS AND STRUCTURES
Before beginning any work involving the placement and driving of metal
plates, it is necessary to remove all types of existing structures and
installations such as roots, or tree stumps that might exist in the driving
zone. Once the preliminary tracing and leveling work is done, it will
be necessary to precisely locate the spot on the field where the cofferdam
plates will be driven.
STAGE II. - GUIDE INSTALLATION
Once the previous stage is completed, a guide will be placed over a surface
2.50 m above the natural terrain, which will be used to maintain the base
of the metal plates steady during driving, as well as to prevent lateral
deviations in any of the plates to be driven. The position and orientation
given to each metal plate will have to be placed perfectly on site.
Once the plate positions are set are set, a ditch with an approximate
depth of 2.50 m will be dug with a 235 Cat backhoe loader.
Next, a metal frame (made of joists and 12” x 8” IPR profile
stamped steel previously soldered with 1/8” E-7018 solder) is placed
inside the excavation site and leveled according to the projects leveling
benches. The soldering will only require visual inspection by the project’s
resident engineer since it is only provisional piling work.The ditch will
then be partially covered with the excavation material, so that the guide
frame will be fixed in place, and the 1.26 m thick and 12.2 m long steel
plates can be driven in pairs, making sure they are properly leveled and
plumed.
STAGE 111. - COFFERDAM PLATE
DRIVING
The plates will be made from profiles type AZ13 structural, in 1.26 m
wide and 12.2m long pairs.
The cofferdam plate driving process has been divided into to phases which
will be carried out simultaneously with some restrictions outlined later.
The phases are as follows.
PHASE 1. -COFFERDAM PLATE LINEUP
The cofferdam plates will be lined up over the natural terrain surface,
and they will consist of a group of 4 metallic plates maximum, which will
be numbered and coupled, making sure to properly grease up the joints
as they are joined; and with the use of a crane with a sufficiently long
arm, they will be hoisted and placed in the previously installed guide.
PHASE 11. - PANNEL
DRIVING
Once phase 1 is completed, mechanical equipment with sufficient power
will be used to drive the cofferdam plates. Once a plate is placed on
the guide with its bottom end of the lying within the space defined by
the guide, the driving of the cofferdam plate will proceed while minding
the following guidelines:
- The placement of the first plate should be done in one of the extremes
of the metallic sheet piling that is being placed.
- In order to place a second panel, the previous one must have been driven
all the way flush with the surroundings.
- Every piece of the cofferdam should be correctly joined to the previous
piece, except for the access port corners.
Once each of the steel plates has been driven, the head level is obtained,
and this level must be verified to conform to the project’s specifications
once all the cofferdam plates have been driven.The plates will be embedded
to 0.5 times the maximum depth of excavation.
Their length will be 12.2m.The cofferdam metal plate driving should be
done in such a way that correct placement of the plates is guaranteed,
so that the project’s objective can be met.
Furthermore, the driving process should not cause any damage to neighboring
structures and installations.
STAGE V. - COFFERDAM PANEL EXTRACTION
The extraction of the cofferdam metal plates should be done once
the pipe-jacking work has been completed.
The extraction of the plates will depend on the quality of the driving
work done previously. A well driven cofferdam will be much easier to extract
than one who’s elements are twisted, separated, or misaligned.
3.- IMPORTANT NOTES
1. -A greasing compound must be used on the joining surface of
all cofferdam plates in order to reduce friction.
2. -The vertical orientation of all cofferdam plates should be
closely observed and verified during the driving process. Any deviation
tendencies that may be displayed must be immediately corrected.
3. - In order to obtain good alignment and vertical control of
all cofferdam plates during placement, the use of a crane is recommended
to minimize the risk of experiencing driving difficulties and alignment
deviation problems.
4. - During the hoisting and driving processes involving cofferdam
panels, the vertical orientation and alignment of their walls should be
verified with an art plumb.
|