PIPE RESTITUTION
THROUGH THE USE OF POLYESTER RESIN MORTAR REENFORCED WITH FIBER
GLASS DUE TO FAILURE
(FRACTURE) |
|
|
1.- Vehicular Transit
Rerouting |
2.- Signposting. |
|
|
3.- Piping supply. |
4.-Access port construction. |
|
|
5.- Access port excavation. |
6.- Cleaning of existing
pipe. |
|
|
7.- Damaged
pipe. |
8.-Pipe cleaning and draining
equipment |
|
|
9.- Cleaning for chamber
introduction. |
10.- Introduction of inflatable chamber to
stop flow |
|
|
| 11.- Joint clearing for the introduction of
new piping. |
12.- Hoisting maneuvers to introduce new piping. |
|
|
13.- Pipe-jacking (driving)
of new pipe. |
14.- Annular stuffing. |
|
| 15.- Finished pipe restitution. |
|
 |