RIO BECERRA COLLECTOR

PIPE RESTITUTION THROUGH THE USE OF POLYESTER RESIN MORTAR REENFORCED WITH FIBER GLASS DUE TO FAILURE

(FRACTURE)



1.- Vehicular Transit Rerouting
2.- Signposting.

3.- Piping supply.
4.-Access port construction.

5.- Access port excavation.
6.- Cleaning of existing pipe.

7.- Damaged pipe.
8.-Pipe cleaning and draining equipment

9.- Cleaning for chamber introduction.
10.- Introduction of inflatable chamber to stop flow

11.- Joint clearing for the introduction of new piping. 12.- Hoisting maneuvers to introduce new piping.

13.- Pipe-jacking (driving) of new pipe.
14.- Annular stuffing.

15.- Finished pipe restitution.